CONGLOMERATES: Litton's Sad Litany
Only half a year ago, Roy Ash, president of California's Litton Industries, sounded like a man who had seen light at the end of a tunnel. Profits of the troubled conglomerate in 1972, he confidently predicted, would increase substantially over their lackluster showing of $50 million in 1971, and one reason for the gain would be Litton's $ 130 million shipyard in Pascagoula, Miss. Ash calls the ultramodern facility, opened about two years ago, "a national asset that will make U.S. shipbuilding competitive in world markets."
In the months since then, Litton's light has dimmed considerably. The company lost money during two quarters of its 1972 fiscal year, and will close the books later this month with what Ash now calls only a "small profit." The trouble stems in large part from the Pascagoula yard, which has produced a small armada of labor problems, construction delays, cost overrunsbut so far very few ships.
Litton's biggest headache is a $752 million order for U.S. Navy general-purpose amphibious assault vessels called LHAS (for Landing Helicopter Assault ships). After the company fell 18 months behind in construction, the Navy slashed the order from nine ships to five. Navy brass caused some of the delay and increased costs by ordering changes in the design. As a result, under the terms of its agreement, the Navy may owe more for the five LHAS it will get than it had planned to spend for all nine. The two parties are currently renegotiating the contract.
Cost estimates are also spiraling upward on a $2.1 billion Navy order for 30 Spruance-class DD-963 destroyers, a new model to be used primarily for antisubmarine duty. Although the contract is designed to hold Litton to fixed prices, it allows for inflation and some other variables that may permit the company to collect additional sums. Some estimates put the eventual cost of each new destroyer at $100 million, v. the $90 million that the Navy deems appropriate; the question is how much of the extra cost will be paid by Litton and how much by the Navy.
Reports of Litton's troubles touched off a furor in Congress, which is growing increasingly impatient with overrun-prone defense contractors. The House Armed Services Committee recently cut next year's budget authorization for the destroyer from $610 million, as requested by the Pentagon, to $247 million. The committee expressed "concern" over costs and delays in both shipbuilding programs, with an eye toward finding remedies.
Game Plan. The Pascagoula plant is also far behind on construction of eight container ships for the Farrell and American President lines. Now scheduled for completion next fall, the first such vessel will be 21 months behind schedule and will cost about double its contract price of $21 million, making it the most expensive general cargo ship ever built. Litton will doubtless pay heavily for the overrun.
- 1
- 2
- NEXT PAGE »
Most Popular »
- And the Decade Goes To ...
- The Pentagon Prepares for a Missile Attack from 'Iran'
- Israel vs. Hizballah: Drumbeats of War
- Tiger Woods' Sponsors: Will Any Stick by Him?
- Detroit's Last White City Council Member
- Yemen's Hidden War: Is Iran Causing Trouble?
- New Zardari Corruption Charges: Bad News for U.S.
- America's Most Wanted Teenage Bandit
- Brief History: The War on Christmas
- New Job for Ex-Soviet Pilots: Arms Trafficking
- Detroit's Last White City Council Member
- America's Most Wanted Teenage Bandit
- Yemen's Hidden War: Is Iran Causing Trouble?
- Super-Earth: Astronomers Find a Watery New Planet
- And the Decade Goes To ...
- Mexico Takes Down a Drug Lord. But Will It Make Any Difference?
- Study: Sunshine States Are Happiest
- China's Domain-Name Limits: Web Censorship?
- New Job for Ex-Soviet Pilots: Arms Trafficking
- Brief History: The War on Christmas





RSS